An Evaluation of Cost Control Measures Applied to Selected Small and Medium Sized Construction Firms.

dc.contributor.authorAdemoroti, Gbadebo
dc.contributor.otherKyere, D. K.
dc.date.accessioned2014-02-12T10:48:50Z
dc.date.accessioned2018-10-27T13:36:57Z
dc.date.available2014-02-12T10:48:50Z
dc.date.available2018-10-27T13:36:57Z
dc.date.issued1986
dc.degree.awardM.Sc. Construction Managementen_US
dc.departmentBuildingen_US
dc.description.abstractThe research determined suitable and effective cost control measures to forestall overrun of contracts by using available resources in Nigerian small/medium sized construction firms. The research data were derived from a survey of seven completed projects and nine selected on-going projects. The questionnaires were divided into four parts. The fit directed to client/financier/ consultants of completed projects determined whether the projects were overrun in terms of time, cost and quality. The second directed to Head office determined cost control measures. The third to supervisors discovered material wastage on site while the fourth to site workforce collected data on labour stability. An observational technique was used to collect additional information about wastage of building materials on the site. An in-depth analysis was carried out on weather data collected from meteorological services. The analysis of the data showed that projects overran either in terms of cost or time. The main cause of cost overrun was attributed to inflation in cost of building materials and time overrun was due to delay in stage payment by the client and bad weather. Based on a model of different sizes of construction firms derived from literature review, observation revealed that small and medium sized construction firms could manage projects up to N250,000.00 and N2,000,000.00 respectively. Emanating from this study, it is recommended that there should be pre-contract arrangement whereby all materiel needed for the project are purchased and kept in a store. The manufacturing of locally produced building materials should be intensified. The contractor should make use of meteorological service reports for the purpose of estimating, planning and control of construction projects. An establishment of an insurance policy bound should be encouraged to protect the contractor from client's failure to honour certificate of payment.en_US
dc.facultiesEnvironmental design and managementen_US
dc.format.filetypePDFen_US
dc.identifier.citationAPAen_US
dc.identifier.urihttp://localhost:8080/xmlui/handle/123456789/2306
dc.language.isoenen_US
dc.pages.totalpages239pen_US
dc.publisherObafemi Awolowo Universityen_US
dc.subjectCost control measuresen_US
dc.subjectconstruction firmsen_US
dc.titleAn Evaluation of Cost Control Measures Applied to Selected Small and Medium Sized Construction Firms.en_US
dc.typeThesisen_US
Files
Original bundle
Now showing 1 - 1 of 1
Loading...
Thumbnail Image
Name:
An Evaluation of Cost Control Measures Applied to Selected Small and-M.Sc.pdf
Size:
38.28 KB
Format:
Adobe Portable Document Format
Description:
License bundle
Now showing 1 - 2 of 2
Loading...
Thumbnail Image
Name:
license.txt
Size:
1.71 KB
Format:
Item-specific license agreed upon to submission
Description:
Loading...
Thumbnail Image
Name:
license.txt
Size:
0 B
Format:
Item-specific license agreed upon to submission
Description: